The African Development Bank Group’s Board of Directors has approved a €71 million loan for a wastewater treatment complex in North Monastir, Tunisia, designed to expand treated-water reuse, protect the Mediterranean coastline and strengthen climate resilience.
The North Monastir Wastewater Treatment Complex will allow treated wastewater to be reused in agriculture and industry while helping safeguard Monastir Bay and the aquaculture activities that depend on it, the African Development Bank (AfDB) said.
The project carries a total cost of €97.91 million. Alongside the AfDB loan, financing includes a €17 million loan and a €1.2 million grant from the Rome Process/Mattei Plan Financing Facility. Tunisia’s National Sanitation Office (ONAS), which will implement the project, is contributing €8.71 million.
About 80,000 residents in the North Monastir area are expected to benefit from improved environmental conditions.
Two treatment plants, greater water reuse
The complex will include two separate wastewater treatment plants. One, with a capacity of 13,200 cubic metres per day, will treat domestic wastewater. The other, with a capacity of 6,000 cubic metres per day, will treat industrial effluents, particularly from the Monastir Industrial and Technology Park.
The new facilities will replace, among others, the ageing Sayada wastewater treatment plant. They are expected to cut pollutant discharges into the environment, protect Monastir Bay and its marine ecosystems, and improve living conditions for local communities.
A central goal is to produce treated wastewater suitable for agricultural and industrial use. The project aims to support irrigation of around 70 hectares of farmland and supply water to at least six industrial enterprises, reducing pressure on conventional water resources.
Solar power and jobs
The complex will also feature a solar photovoltaic installation with a capacity of about 3.6 megawatts-peak (MWp). It is designed to meet nearly 30% of the facility’s electricity needs, lowering energy costs and greenhouse gas emissions.
The AfDB said the project is expected to generate about 1,000 temporary jobs during construction and 50 permanent direct jobs in operation and maintenance. In addition, 500 ONAS officials and technicians will receive training.
“This project addresses three critical challenges for Tunisia: improving people’s quality of life, protecting the coastline from pollution, and harnessing treated wastewater as a resource for agriculture and industry,” said Malinne Blomberg, Deputy Director General of the African Development Bank Group for North Africa and Country Manager for Tunisia. “By combining sanitation, water reuse and solar energy, the Bank will help strengthen the country’s long-term water security and climate resilience.”
Aligned with national strategy
The AfDB said the project is aligned with Tunisia’s 2026–2030 National Development Plan, its national Water 2050 Strategy and the Bank Group’s 2024–2029 Country Strategy Paper.
It is expected to contribute to sustainable water management, stronger climate resilience and economic development in the Monastir region.
TunisianMonitorNews